From the desk of GSH-BOD Chairman

Our Construction team is working very hard and currently concentrating on interior works. From outside it may look that no progress are made, sometime looks are deceptive and give wrong impression.

unfortunately we could not provide photos of the construction for the last few months due to improper lighting inside the building.

We finalized our stub to work simultanously with our contractor to espedite and finsish this work.

All interior partition walls are complete and ready for insulation and sheet rock. Electrical wiring is almost complete and will have city inspection soon. Sprinkler system is already in place.  All ceiling support framing is complete. Front canopy work is complete.

One roof drain on east side of the building is connected to the ground storm line ground will be cleared and all the debris will be carted away. Next Step will be to finish all paving including connection to Ruffiino Road and installing culvert.

Last couple of days the excessive heat has attected our progress as workers production slowed down.

As I said in beginning that the last seven months was a gental reminder what we were doing and last five months of the year will kepp us on the path to accomplish our goal.

Thank you

Dr. Harshadbhai Patel

GSH-BOD Chairman